A time bar usually bars: a notice missed by a day loses the entitlement on merits nobody reaches. Where a court may now relieve one, the evidence decides, and the agent keeps it.
- Typical delivery
- 4–6 weeks
- Deployment
- Your stack
- Planner review
- Drafts only
- After launch
- Agent Care
What this agent does
Computes the deadline; it does not serve the notice
In
- 01
Compute the notice-deadline register from the clocks and triggers your executed contract sets.
- 02
Diff each programme revision against the last — activity, duration, tie and calendar.
Reason
- 03
Archive every revision immutably, with its author, timestamp, data date and provenance.
- 04
Compute time elapsed on each open item and escalate long before the window closes.
- 05
Diff field progress against the model and flag as-built dates no record supports.
Decide
- 06
Diff the model against the accepted programme and flag drift instead of closing it.
- 07
Route every register item and every draft to the planner who holds it.
Out
- 08
Archive the records read, the draft, the amendments and the decision against the event.
- 09
Execute write actions only inside the approval boundaries agreed during implementation.
Product statement
The agent computes deadlines and drafts; the contracts administrator serves the notice — and a date that has passed cannot be un-passed by anyone.
Example workflow
One delay event, record to draft
- 1Delay event recordedSite diary, progress update, instruction or correspondence
- 2Clocks resolvedThe notice periods, triggers and escalation steps configured from the contract as executed
- 3Register item computedDeadline, time elapsed and confidence
- 4Controls appliedConfigured-clock checks, evidence checks, escalation timers and confidence threshold
No human action required
Stages 1 to 4 run unaided, and nothing is served at any of them — the agent is computing deadlines, and the planner's lane opens at the confidence gate.
Goes to the planner who holds it.
Adds a contracts read first.
Planner review
The item is held with its deadline, the records behind it and the confidence.
Acknowledge · Amend draft · Send to contracts
Acknowledged — back with contracts
- 6Schedule systems updatedOnly where write access and approval policy allow it
- 7Outcome evaluatedEscalation lead time, drafts amended, notices served and events that ran past the window
Amendments
Every amendment made in review is counted in the evaluation.
What should not run autonomously
Human approval stays in control
Outside the boundary — human approval required
8 items
- Serving or transmitting any contractual notice.
- Approving, rejecting or accepting a programme submission.
- Changing the baseline, data date, calendars or logic.
- Selecting the delay-analysis method.
Automation boundary
Agent acts unaided
- ✓Compute the notice-deadline register with escalation timers for each named owner.
- ✓Diff two programme revisions, activity by activity.
- ✓Reconcile field progress against the model.
- ✓Archive every revision with its author, timestamp and provenance.
Any write happens inside the boundaries agreed at implementation, and never into the live programme.
- Characterising delay as excusable, compensable or concurrent.
- Certifying, waiving or forecasting liquidated damages.
- Declaring time at large, or a claim time-barred.
- Releasing a schedule or forecast outside the project.
Example output
One register item, annotated
Everything the agent computes is attached to the records it was read from.
Register item · single delay event
Illustrative example- Package
- Piling subcontract
- Delay event
- Access to the piling zone withheld by the principal
- Window elapsed
- 52% elapsed
- Item state
- Escalated — draft with the planner
- Confidence
- 93%
- Clock source
- The contract as executed
As received
Taken from the site records and the clocks configured for this contract — nothing on this side is written by the agent.
What was read
- Site diary entry
- Accepted programme revision
- Correspondence log
Why this deadline
The period comes from the contract as executed and amended.
What the score decides
Below the configured threshold the item picks up a contracts read before the planner sees it.
Action
AcknowledgeAmend draftSend to contractsValue
Where AI adds value
The same four claims, placed at the point in the workflow where each one applies.
Where the value lands
Value 01 – 04
Every delay event
From records and the contract
Apply the contract as executed
Standard forms are almost always amended, so the agent works from the clocks configured for your contract, not the printed form.
See the bar before it closes
Routine register items and revision diffs arrive already computed.
Send review to the tight clocks
Short windows and low-confidence items are marked, so the planner's read starts where the clock is tightest.
Build an evidence trail
Every revision keeps its author, its timestamp and the diff that produced it.
Integrations
Typical integrations
Five system groups connect to the same agent. Which of them are in scope is decided in discovery.
CPM scheduling engines
- Oracle Primavera P6
- Asta Powerproject
- Microsoft Project
- Deltek Open Plan
Schedule analytics
- Deltek Acumen Fuse
- SmartPM
- Revision exports and progress updates
Field progress capture
- Procore
- Autodesk Construction Cloud
- Site diaries and daily records
Agent
Project schedule & delay notices
- Reads the records
- Computes the deadlines
- Holds for the planner
Contract and document backbone
- Oracle Aconex
- Trimble Viewpoint
- Notice and contract registers
Observability & evaluation
- OpenTelemetry
- Langfuse
- Supported monitoring/evaluation sources
Integration availability depends on the client's existing systems and API access.
Agent controls
Six layers between the model and the notice
Each control wraps the one inside it. What a layer does not catch is named in the failure-mode map below it.
L6 · Outermost — last line of defence
Inward → L1 · closest to the model
- L1 – L2
- Test whether an item may stand
- L3
- Puts the decision in the planner's hands
- L4 – L5
- Hold the revision history the claim rests on
- L6
- Stops drafting when evaluation signals slip
How Nestack evaluates it
Evaluate the notice workflow — not only the finished programme.
Coverage runs the whole depth of the workflow, and every layer is cut by slice.
Surface — the deadline the project acts on
- E1Final-output evaluationWas the deadline computed from the clock this contract actually sets?
- E2Step-level evaluationDid the agent read the right revision, records and contract configuration?
- E3Tool evaluationDid it read and write the correct project and the correct register?
- E4Confidence calibrationDo low-confidence items actually attract more planner amendments?
- E5Slice evaluationHow does performance change across specific contract forms?
- E6Business outcomeHow many events needed an amendment, or ran past the escalation window?
Floor — the entitlement the contractor keeps
Failure modes
Where each failure originates in the agent
Seven failure modes, plotted at the stage where each one begins.
Agent lifecycle
Direction of processing →
01 · Retrieval
1 mode
- PJ-01
Unaccepted revision pulled
Analysis runs against a programme that was never the datum.
Stage gathers
Revisions, site records, progress updates and configured clocks
02 · Reasoning
2 modes
- PJ-02
Float read as no delay
Float consumed by an employer risk event is reported as no impact.
- PJ-03
Concurrency from overlap
Calendar overlap is read as concurrent delay to completion.
Stage proposes
Deadline, time elapsed and confidence
03 · Tool / write
2 modes
- PJ-04
Live programme rewritten
A revised data date and re-levelled resources erase the as-planned logic.
- PJ-05
Register item auto-closed
An item closes as no entitlement and the escalation clock stops.
Stage writes
Only where write access and approval policy allow it
04 · Output
1 mode
- PJ-06
Forecast reads as an admission
Client-facing wording concedes contractor culpability.
Stage returns
The register the planner reads before serving
05 · Change / Version
1 mode
- PJ-07
Silent calendar change
A tool upgrade shifts retained logic, so the longest path moves.
Stage tracks
Model, prompt, calendar defaults and contract config
- Sev-1 · a held act performed by the agent
- Sev-2 · a wrong deadline reaches the planner
- Sev-3 · records degrade, item routes to review
Affected slices
A steady average can rest on one contract form
The all-event baseline is the number a monthly report shows; underneath it a small set of contract cohorts absorbs most of the late escalations. Nestack reports the rate by slice, not only in total.
Slice performance — reported separately, not only in aggregate
Illustrative example| Slice | Failure rate | Lift | Lift vs. threshold | Status |
|---|---|---|---|---|
| FIDIC and NEC EPC packages | 5.9% | 3.7× | Review | |
| AS 4000 head contracts | 4.0% | 2.5× | Review | |
| JCT and A201 traditional build | 2.4% | 1.5× | Watch | |
| Framework programmes | 0.8% | 0.5× | Normal |
Bar: late-escalation-rate lift vs. an all-event baseline · scale 0–4.0× · tick marks the 2.0× review threshold
2 of 4 slices over threshold
Evidence-linked improvement
Nothing closes until the suite grows
The loop shuts when the miss is a case in the suite, not when someone has explained it.
Improvement cycle · five stages
Switchback — the path turns at Improve and returns at Learn
- 01
Detect
Late-escalation rate rises in a contract-form slice.
- 02
Diagnose
Not isolated until the archive, the records and the register agree on one cause.
- 03
Improve
Whatever changes ships against a version, with the notices that prompted it attached.
- 04
Verify
Nothing ships until the affected cases pass a second time.
- 05
Learn
The suite grows by one case; so does the notice playbook.
Learn → Detect
The return edge. Detection next time runs against a longer suite.
Typical build scope
Twelve workstreams across six weeks
The build scope read against the delivery timeline. Week structure follows the six-week plan — discovery, sources, notice workflow, evaluation, integration, then production validation and handover.
Workstream
Week 1Week 2Week 3Week 4Week 5Week 6
- 01Programme workflow discovery and boundary work.Week 1
- 02Schedule and field-record assessment.Week 1, Week 2
- 03Contract-clock, calendar, float and notice-rule mapping.Week 1, Week 2
- 04Programme ingestion and normalisation.Week 2
- 05Deadline computation and revision-diff logic.Week 2, Week 3
- 06Confidence scoring and register-item routing.Week 3
- 07Planner review workflow.Week 3, Week 4
- 08Scheduling and document-system integration.Week 5
- 09Notice-timing regression cases.Week 4, Week 5
- 10Guardrails and service controls.Week 4
- 11Revision-archive instrumentation.Week 5, Week 6
- 12Deployment, documentation and Agent Care handover.Week 6
12 workstreams · 6 weeks · bar shows the weeks a workstream is active — several run in parallel
Final scope and sequence confirmed in discovery
Engagement tiers
What each tier includes
Rows are the capabilities named in each tier's scope. Higher tiers include everything below them.
| Capability✓ in scope · — not at this tier | PilotOne project, one contract form | ProductionProduction scheduling systems | AdvancedMultiple projects / forms |
|---|---|---|---|
| Introduced at Pilot | |||
| Deadlines from your executed contract | ✓ | ✓ | ✓ |
| Planner review | ✓ | ✓ | ✓ |
| Notice-timing baseline | ✓ | ✓ | ✓ |
| Introduced at Production | |||
| Reporting by contract form | — | ✓ | ✓ |
| Review workflow in your systems | — | ✓ | ✓ |
| Approved write-back | — | ✓ | ✓ |
| Client and funder reporting feed | — | ✓ | ✓ |
| Introduced at Advanced | |||
| Multi-form portfolios | — | — | ✓ |
| Multi-stage contract review | — | — | ✓ |
| High event volume | — | — | ✓ |
| Enterprise programme controls | — | — | ✓ |
| Build price | From $5,000 | From $8,000 | Custom quote |
- Final build price
- Confirmed after discovery based on integrations, workflow complexity, event volume, approval controls and deployment requirements.
- Separate from build
- Build pricing is separate from recurring Agent Care, which covers managed monitoring, evaluations, incidents and verified improvements after launch.
What we need from you
What you bring, and what we build with it
Each input maps to a piece of build scope and a week in the delivery timeline.
You bring
We build with it
01Your contract forms and their executed amendments
→Contract-clock and trigger mapping
Week 102Representative programme revisions
→Deadline baseline, revision diffing and progress reconciliation
Week 203Your notice register and escalation practice
→Escalation-timer mapping and automation-boundary definition
Week 104Access to relevant APIs, feeds or exports
→Scheduling, field and document assessment, then integration setup
Week 205Delay events you did not notice in time
→Notice-timing cases and the evaluation suite
Week 406Where a draft notice stops and waits for the planner
→Confidence scoring, item routing, guardrails and approval controls
Week 307Named planners to review the register
→Planner review workflow, then pilot and production validation
Weeks 5–6
Nothing else is required
Deployment, documentation and Agent Care handover are ours.
Delivery timeline
Four phases across six weeks
Each phase is drawn across the weeks it truly occupies. Week 5 carries evaluation and pilot at once.
Phase
W1
W2
W3
W4
W5
W6
- DiscoveryW1
- BuildW2 – W3
- EvaluateW4 – W5
- Pilot & LaunchW5 – W6
Week focus
W1Programme workflow discovery, clock mapping and the automation boundary
W2Source integration and the deadline baseline
W3Diff logic, confidence scoring and review controls
W4Evaluation suite, guardrails and failure-mode testing
W5Scheduling-system integration, pilot events and targeted corrections
W6A full monthly programme cycle under the planner, then handover
- Reading the band
- Each bar covers the weeks its work is named in and no others. The week 5 overlap is real, not padding.
- At the end of W6
- Once the cycle validates, Agent Care owns the running agent.
- Duration
- Six-week plan shown · typical delivery 4–6 weeks depending on scope confirmed in discovery.
Next step · Construction AI agent
Build a project-schedule agent around your notice clocks.
Show us your contracts as executed, your programme revisions and who serves the notice. Once a window closes the entitlement closes with it, so we map the clocks first and name what the agent never touches.
- Typical delivery
- 4–6 weeks
- Deployment
- Your scheduling stack
- Planner review
- Drafts only
- After launch
- Agent Care available
Nestack Agents · Project schedule and delay notices
AGT-CN-03 · Agent Care available after launch